Some more progress has been made on the toilets. As I mentioned to you in the past that the work on the toilets had stopped due to several reasons. First it was due to lack of funds, and fortunately we found a willing donor. Then Mr. Bhalke was indisposed due to several personal challenges. When we sorted these out, the contractor left the work mid-way and absconded. We lost a few months due to this. Finally, Mr. Kiran Yepre decided to help us and took the responsibility of building the toilets. But, due to the Gram Panchayat elections, he was also got very busy and we lost a few months. Here, we can see the progress we have made from nothing to something...but we still have a long way to go... |